NEC® Changes · 2020 NEC®

517.17 Ground-fault protection (health care)

RevisedChanged in the 2020 NEC® (from the 2017 NEC®)· Updated October 24, 2026

What changed in 517.17

Ground-fault protection testing in health care facilities must now be done by a qualified person following the equipment instructions, with results available to the inspector.

Point by point

  • Every level of ground-fault protection still has to be performance tested when it's first installed.

The full lesson is in the Pro Version

Get the whole breakdown

  • 3 more points on exactly what changed
  • The 2017 rule next to the 2020 rule, side by side
  • Why it changed
  • What to do and check on the job

One membership unlocks every NEC® change lesson for 2020, 2023 and 2026, plus every video, quiz, flashcard and the Testing Center.

Checking your membership…

This section across NEC® editions

2020 NEC®RevisedYou're here

Ground-fault protection testing in health care facilities must now be done by a qualified person following the equipment instructions, with results available to the inspector.

2023 NEC®No change

This section did not change from 2020 to 2023.

2026 NEC®Revised

Health care GFPE in 517.17 was rewritten: automatic-trip GFPE isn't required from on-site sources up to essential system transfer switches or on their load side, and every on-site source now needs ground-fault indication.

Open the 2026 page →

More 2020 changes in Article 517

This is a plain-English summary, not the NEC®'s exact wording. Always check the full section in the NEC® edition your area has adopted, plus any local amendments.

NEC® and National Electrical Code® are registered trademarks of the National Fire Protection Association (NFPA). Electrical Exam Coach is not affiliated with or endorsed by NFPA.

Find it faster on test day

Get a code book that's already tabbed and highlighted.