695.6 Fire pump power wiring
What changed in 695.6
Fire pump supply conductors inside the fire pump room no longer need to be under or encased in concrete, and a new note points to the neutral routing rule in 250.24(C).
Point by point
- Fire pump service and on-site power conductors still need to run outside the building when they can.
The full lesson is in the Pro Version
Get the whole breakdown
- 3 more points on exactly what changed
- The 2017 rule next to the 2020 rule, side by side
- Why it changed
- What to do and check on the job
One membership unlocks every NEC® change lesson for 2020, 2023 and 2026, plus every video, quiz, flashcard and the Testing Center.
Checking your membership…
This section across NEC® editions
2020 NEC®RevisedYou're here
Fire pump supply conductors inside the fire pump room no longer need to be under or encased in concrete, and a new note points to the neutral routing rule in 250.24(C).
2023 NEC®Revised
Fittings for the cable and raceway between the fire pump controller and motor must now be listed for wet locations.
Open the 2023 page →2026 NEC®No change
This section did not change from 2023 to 2026.
More 2020 changes in Article 695
This is a plain-English summary, not the NEC®'s exact wording. Always check the full section in the NEC® edition your area has adopted, plus any local amendments.
NEC® and National Electrical Code® are registered trademarks of the National Fire Protection Association (NFPA). Electrical Exam Coach is not affiliated with or endorsed by NFPA.